Oops, They Did It Again! Queens-Midtown Tunnel Reopens After Contractor's Leak
The Queens-Midtown Tunnel reopened to traffic after a contractor accidentally drilled a hole in the tunnel's roof, causing water from the East River to leak in.
The incident occurred around 12:30 p.m. on Wednesday, causing both tubes of the tunnel to be closed initially. The north tube reopened around 3 p.m., while the south tube reopened at 5:45 p.m. after the MTA temporarily plugged the leak.
Mayor Eric Adams described the leak as "small," while officials said the contractor was performing investigative work for a new segment of the East River Esplanade. The drill, lowered 50 feet through the water, then another 50 feet through the ground, damaged the tunnel tube.
The MTA initially announced the cause as a water main break, but later acknowledged the mistake.
The tunnel is now safe for traffic, but the MTA is working on a permanent solution to the leak.
The Queens-Midtown Tunnel: Some Facts You May Not Know
Opened in 1940, the Queens-Midtown Tunnel connects Hunters Point in Long Island City, Queens, to Murray Hill in Manhattan. Each tube has two lanes and is over 7,400 feet long - roughly 1.4 miles. Approximately 90,000 vehicles pass through the tunnel each weekday.