7 train repairs at 52 St and 69 St run five months longer as costs climb to $254 million

Inspectors found 22 more deteriorated steel sections under the Flushing-bound platforms in Woodside, so the skip-stop detour that began in May keeps going. Here's how to get to and from the two stations.

Written by NewYorkNews NewsroomNov 1, 2026 · 2 min read · 3 sources
The Manhattan-bound platform at the 52 St-Lincoln Av station on the elevated 7 line in Queens, with a green 52 Street sign
The Manhattan-bound platform at 52 St on the 7 line in 2026. Flushing-bound trains skip the station during repairs.

Photo: Transitsylveonkpop / Wikimedia Commons · CC BY-SA 4.0

Key points
  • The platform rebuild at 52 St and 69 St on the 7 is now expected to finish in March 2027 instead of Oct. 20, the New York Post reported, citing MTA documents.
  • Inspectors found 22 more deteriorated sections of the steel beams under the Flushing-bound platforms; the new work adds $2.8 million, bringing the contract to about $254.4 million from $217 million.
  • Flushing-bound 7 trains have skipped both stations since May 25; the MTA's notice says the skip runs through spring 2027.
  • To reach either station, ride to Woodside-61 St or 74 St-Broadway and take a Manhattan-bound 7 back; to head toward Flushing, ride to 46 St-Bliss St or Woodside-61 St and switch to a Flushing-bound 7.
  • The MTA's project page lists 52 St and 69 St among 7-line station renewals due in 2027, with new platform edges, ADA boarding areas, stairs, lighting and cameras.

Riders who use the 52 St and 69 St stations on the 7 in Woodside, Queens, will keep doubling back for months longer than planned. The platform reconstruction is now expected to finish in March 2027, nearly five months after its previous Oct. 20 target, the New York Post reported Sunday, citing MTA documents.

According to those documents, inspectors found 22 more deteriorated sections of the steel beams holding up the Flushing-bound platforms at the two stations. Fixing them adds $2.8 million to a contract that started at $217 million. Earlier changes had already added $34.5 million, partly for the cost of resequencing the work, bringing the total to about $254.4 million, roughly 17% over the original price, the Post reported. An MTA spokesperson told the paper that crews often can't see how badly steel has deteriorated until they open up the structure.

How to get around the detour

Since May 25, Flushing-bound 7 trains have skipped 52 St and 69 St while the platforms are rebuilt, as amNY reported when the MTA announced the change. The MTA's service notice now says the skip runs through spring 2027. Manhattan-bound trains still stop at both stations.

  • Going to 52 St or 69 St from Manhattan: Ride to Woodside-61 St or 74 St-Broadway, then take a Manhattan-bound 7 back one stop.
  • Leaving 52 St or 69 St toward Flushing: Take a Manhattan-bound 7 to Woodside-61 St or 46 St-Bliss St, then switch to a Flushing-bound train.
  • Nearby stations: 46 St-Bliss St, Woodside-61 St and 74 St-Broadway, where the 7 connects with the E, F, M and R.
  • Woodside-61 St: When the long-term change started, the MTA said all trains there would board from the Manhattan-bound platform, and that temporary platforms would be in place at 33 St-Rawson St, 40 St-Lowery St and 46 St-Bliss St, amNY reported.

What riders get at the end

The MTA's 7-line project page says the work at both stations includes new platform edges and ADA-compliant boarding areas, new stairs, new mezzanine floors and platforms to remove uneven surfaces, windscreens, artwork, paint, lighting and CCTV cameras. The page lists 52 St and 69 St among station renewals to be completed in 2027, along with 82 St-Jackson Heights, 111 St and 103 St-Corona Plaza.

This is not the first time steel problems have pushed back the 7-line work. The overhaul was supposed to wrap up in 2025, but the MTA said it found severe, unforeseen deterioration in the steel supports above Roosevelt Avenue, including at Woodside, amNY reported.

Check the MTA app or Planned Service Changes before you ride, since weekend and overnight work along the line can add other changes.

Advertisement
Filed underTransit
How this story was madeWritten by NewYorkNews Newsroom from 3 sources · Nov 1, 2026

Every story links to the reporting and records it’s based on. Our editors write each piece from public reporting and official data, and check it against those sources before it’s published.

Comments

0In Community

Your comment is also posted to Community with this story attached, so neighbors can find it and reply there too.

Sign in to join the conversation with your neighbors.

No comments yet

Start the conversation — your comment shows up here and in Community for neighbors nearby.