Port Authority set to approve $117.5M fix for the Trans-Manhattan Expressway after falling debris hit cars
The board votes Thursday on a full structural rehab of the sunken GWB approach in Washington Heights, where a metal piece and a chunk of concrete fell on drivers in May. Construction would start next year and run to 2030.

Photo: Famartin / Wikimedia Commons · CC BY-SA 4.0
- The Port Authority board is set to vote Thursday on $117.5 million to rehabilitate the structure of the Trans-Manhattan Expressway, the approach that links the George Washington Bridge to city streets and the Cross Bronx Expressway.
- In May a piece of metal fell from the roadway's ceiling, and six days later a chunk of concrete hit a car and sent the driver to the hospital, Gothamist reported.
- Board documents say the structure has not had a comprehensive rehab since it was built and that inspections after May found deficiencies needing immediate repairs.
- The plan removes the metal panel ceilings and adds permanent protective mesh to catch overhead debris; design runs to Q3 2027, construction from Q3 2027 to Q3 2030.
- The money is moved up from four projects that had been planned for later in the agency's 2026-2035 capital plan.
The Port Authority is preparing a $117.5 million overhaul of the Trans-Manhattan Expressway, the sunken, partly covered stretch of highway in Washington Heights where falling debris struck drivers twice in May. The agency's board is scheduled to vote on the project at its meeting Thursday, and Gothamist first reported the plan Wednesday.
The expressway runs about 0.8 miles beneath buildings in Upper Manhattan and connects the George Washington Bridge's lower level to local streets and the Cross Bronx Expressway. It opened to drivers in the early 1960s.
What happened in May
On May 7, a piece of metal fell from the roadway's ceiling, and a driver who crashed into the debris caught the moment on camera. Six days later, a chunk of concrete fell onto a car and the driver was hospitalized, Gothamist reported. Port Authority Executive Director Kathryn Garcia has blamed months of freezing and thawing last winter for the deterioration. The agency made emergency repairs at the time.
What the board is being asked to approve
- Why now: the structural elements at the expressway level "have not undergone comprehensive rehabilitation since their original construction," the board documents say. Inspections after the May incidents found deficiencies requiring immediate repairs and led the agency to speed up rehab work it had planned for later.
- The work: repairs to concrete and steel in the overpasses, joints, piers, beams and soffits and some retaining walls; removal of the existing metal panel ceilings; and permanent protective mesh to catch overhead debris. Traffic would be maintained on the expressway and the bridge during construction.
- Timeline: design from late 2026 to the third quarter of 2027, then construction from the third quarter of 2027 to the third quarter of 2030.
- Cost breakdown: of the $117.5 million, $71.3 million is for a construction contract to be publicly advertised, $20.4 million for planning and design, $14.1 million for contingency and $11.7 million for agency costs. The board would also raise an existing design contract with Arora and Associates from $7.8 million to $12 million.
- Where the money comes from: four projects that had been slated for the second half of the agency's 2026-2035 capital plan, including $42.5 million earmarked to replace the ceiling over the expressway and $45.6 million for the next phase of overpass repairs.
A Port Authority spokesperson told Gothamist the agency could not comment before the board votes.
Part of a bigger GWB overhaul
Thursday's agenda includes several more George Washington Bridge items, among them rehab of the bridge's upper-level deck and the bus parking bridges over Broadway. They fall under "Restoring the George," a roughly $2 billion program to modernize the 95-year-old bridge, which recently reopened its rebuilt South Walk to pedestrians and cyclists.
- GothamistPort Authority eyes $117M fix to Manhattan roadway where falling debris smashed cars
- Port Authority of New York and New JerseyPublic agenda, Board of Commissioners meeting, Oct. 22, 2026
Every story links to the reporting and records it’s based on. Our editors write each piece from public reporting and official data, and check it against those sources before it’s published.
Comments
0NSynced with CommunityIn CommunityYour comment is also posted to Community with this story attached, so neighbors can find it and reply there too.
No comments yet
Start the conversation — your comment shows up here and in Community for neighbors nearby.