Queens Botanical Garden's new education center, with a green roof and teaching kitchen, is on track for fall 2027
Officials toured the construction site of the 14,500-square-foot Joan N. and Norman Bluestone Education Center in Flushing, a city-funded building designed to drain its own stormwater.

Photo: Queens Botanical Garden / Wikimedia Commons · CC BY-SA 4.0
- Construction of Queens Botanical Garden's Joan N. and Norman Bluestone Education Center, which broke ground in June 2025, is slated to finish in fall 2027, QNS reported after a hard-hat tour Monday.
- The city put the cost at $34 million when it broke ground; the project is funded mainly by the city and is managed by the Department of Design and Construction.
- The 14,500-square-foot building will have four classrooms, a teaching kitchen, a teaching solarium, offices and meeting rooms, and is aiming for LEED Platinum.
- A green roof with solar panels and a bioswale that sends stormwater to tanks under the site are meant to take the building's runoff off the city sewer system.
- Queens Borough President Donovan Richards Jr. put $4 million into the project, QNS reported.
The biggest construction project in years at Queens Botanical Garden in Flushing is moving toward a 2027 opening. Garden staff and elected officials took a hard-hat tour Monday of the site of the Joan N. and Norman Bluestone Education Center, which is slated to be finished in fall 2027, QNS reported.
The city broke ground on the building in June 2025, when the Department of Cultural Affairs and the Department of Design and Construction put its cost at $34 million and said it would be fully funded and built by the city, according to the city's announcement. QNS described it as an over-$30 million project paid for primarily by the city, with Borough President Donovan Richards Jr. contributing $4 million and support from private donors, including the Bluestone Foundation.
What's inside
The 14,500-square-foot building, designed by BKSK Architects, replaces a smaller education space. Plans include:
- four classrooms for school groups, two of which can combine into one large space for events;
- a full teaching kitchen for adult classes and a teaching solarium where educators can grow plants;
- offices, meeting rooms and a gallery, plus a covered outdoor gathering space;
- a flexible lawn near the main entrance and a Kids' Culture and Discovery Garden, QNS reported.
Built to handle Flushing's water
The building is aiming for LEED Platinum, the top green-building rating, with a living green roof and solar panels. A bioswale planted with water-tolerant species will send stormwater into detention tanks under the site, which BKSK's project manager told QNS will take the burden of the project's runoff off the city storm system. Flushing has a high water table and a history of flooding; Richards pointed to the damage from the remnants of Hurricane Ida in 2021.
Artist William Lamson is designing site-specific stone works from the garden's bedrock and imported stone, including carved channels where visitors can pour water and watch how it drains, according to QNS.
Executive Director Evie Hantzopoulos told QNS the project grew out of the garden's master plan and that the site will look very different by 2028.
- QNSQueens Botanical Garden continues to make progress on $30 million education pavilion
- NYC Department of Cultural AffairsCity Breaks Ground on a New $34 Million Education Building for the Queens Botanical Garden
- BKSK ArchitectsQueens Botanical Garden Education Center
Every story links to the reporting and records it’s based on. Our editors write each piece from public reporting and official data, and check it against those sources before it’s published.
Comments
0NSynced with CommunityIn CommunityYour comment is also posted to Community with this story attached, so neighbors can find it and reply there too.
No comments yet
Start the conversation — your comment shows up here and in Community for neighbors nearby.